The government will recall contractors back to their respective sites to continue with about 100 kilometers of stalled road works in Gichugu Constituency.

The contractors, who allegedly abandoned the sites owing to unpaid claims, will now resume after government settles the pending bills, thus allowing them to operate optimally until completion.

Gichugu MP Robert Gichimu stated that delayed payment of bills has been a huge hindrance to government projects, not only in Kirinyaga, but the entire country. "All stalled roads in Gichugu, approximately 100km of roads, will resume and be completed within the current financial year," he said.

He added that in order to ensure smooth implementation, no other new road will be started, until they first complete the pending ones.